A project risk rarely announces when it becomes a company problem. It starts small, inside a single project, and grows quietly until leadership finally notices. By then, the options are fewer. We sat down with Pasi Rautanen, Director of Management Consulting at KPMG, to discuss how to close that gap, and how the technology partner and the customer can see project risk clearly together.

Estimated reading time: 7 minutes

Read the summary

Every project carries risk. Teams usually manage it one project at a time, while leadership looks at the whole portfolio. That difference in view creates a delay.

Rautanen points to geopolitical tension, rising prices, and higher interest rates as current examples. These changes can disrupt a supply chain and hit a project right away. At company level, the bar is much higher, so the effects may need to accumulate before they show there.

Start with two lists

Rautanen’s first piece of advice is simple. Split your risks into two groups. The first group holds risks you can manage and mitigate. The second holds risks outside your control, such as a new war or a natural disaster. You need to acknowledge these, but you can do little about them.

In Rautanen’s experience, the most common mistake is skipping this step. Teams build a long list that covers everything in the world and lose focus as a result. Instead, once the split is done, teams should rank the manageable risks by impact. Timing matters too, since acting early on the right risk often lowers the exposure quickly.

Know when a risk crosses the line

According to Rautanen, the most general sign is when a risk crosses project boundaries. If the project team can no longer handle it, it has become a company matter.

Some risks deserve that status from day one. Rautanen names reputation as an example. A reputational hit can affect both companies at once and shape future business long after the project ends. “You cannot cross a border on this one,” he says.

That is why teams should look past direct monetary impact when they assess risks at the start. They should ask what the indirect and long-term consequences would be if a risk came true.

Make risk part of the routine

Rautanen admits that risk work can feel less interesting than the project itself, since it deals with what can go wrong. Teams often underestimate how much it needs to be shared. “The sure way to make this go wrong is to give it to one person and one person only,” he says. Risk management should be an essential part of managing the project.

At leadership level, the routine looks different. Leaders can’t follow every risk in every project with the same intensity. According to Rautanen, leadership needs a shared understanding of which projects are strategic and which are financially most important. Every project is still followed, but these get special attention. This way, the right projects stay top of mind.

Share the goals behind the project

Rautanen stresses the importance of shared goals. Both parties want to achieve the project outcomes, and working toward that common goal can lower the risk level considerably. That is why they should also share the bigger goals behind the project.

The stakes may still differ, and one party may face very different risks than the other. For one, the project may open important future opportunities. For the other, it may be just one project among many. Without communication, this difference isn’t clear from the start.

Build the risk picture together

Good collaboration starts with talking things through together, and that includes risks. According to Rautanen, neither party should handle risks alone. Instead, they should list them together.

Openness also makes mitigation work, because some actions need the other party’s help. “If you don’t openly discuss the risks, you might end up having only half of the mitigating actions in place,” Rautanen says.

When both project teams own the risk picture, each can carry the same view to its own leadership. That shared understanding shows both companies how much risk the project carries for them.

Learn from the last project

Learning from past projects is often the biggest blind spot. Without it, the same problems come back. Another trap is hoping that time will fix a risk without any action. Rautanen’s remedy is to share learnings across projects. That includes mitigations that worked and gaps in the risk process that led to failure. “That’s the only way we can be better next time,” he says.

The good news is that it is never too late to start managing risk – there is always room to do it better.

Want to know more? Check out these articles:

Top Engineer Magazine
Trust, failures and coffee breaks – How work communities enable innovation

Technology organizations invest in R&D, yet many struggle to translate that expertise into tangible innovations. We sat down with Antti Arasto, Vice President at VTT, to discuss the conditions that make innovation possible. Three things stand out: it cannot be commanded from above, failure must be tolerated, and human interaction is essential.

Blog
Developing successful CCUS projects

CCUS – capturing CO₂ at the source and storing or reusing it – is moving from pilot projects to large-scale deployment. Within a hydrogen strategy, CCUS raises economic value and supports decarbonization goals.